Workers must comply with any reasonable and cooperative policy and procedures. In case of any incidents, please contact the project manager, Jamie 0433 024 079. PERSONNEL MUST NOTIFY THE PROJECT MANAGER IMMEDIATELY IF ANY DISCREPANCY IS FOUND.
Prepared by: Regina Wong
Reviewed by: Jamie Dong
Date: 5 May 2023
#1 - Preparation
Trainee/ Junior Tradesmen
Prepare water, power tools, ensure batteries are fully charged
Set up mixing station
Prepare back blocking timber, and back blocking cement
Mid-level Tradesmen Check onsite material is same as purchase order and delivery docket.
Please take a photo of onsite material and send to Regina via 0433 799 357 or orders@drywallwa.com.au
Team Leader Prepare cutting list and mentioned if it is for ceiling finish, cornice finish or P50 finish
Double Storey Casual Labour (ensure at least four personnel on site) For loading purpose
#2 - Installing Plasterboard
Trainee/ Junior Tradesmen
Adhesive
Back blocking
Holding sheet
Mid-level Tradesmen + Team Leader Use collated screw gun to screw in, ensure screws are fix 200mm centre to tiles areas
#3 - After Installation
Team Leader
Double check manhole location before cutting it
Mid-level Tradesmen
Ensure drywall lining are square, straight and level.
Cut out the manhole and install the manhole frame
#4 - Cleaning up
Trainee/ Junior Tradesmen
Clean the site every day before leaving