Fixing Procedure

Workers must comply with any reasonable and cooperative policy and procedures. In case of any incidents, please contact the project manager, Jamie 0433 024 079. PERSONNEL MUST NOTIFY THE PROJECT MANAGER IMMEDIATELY IF ANY DISCREPANCY IS FOUND.


Prepared by: Regina Wong

Reviewed by: Jamie Dong

Date: 5 May 2023




#1 - Preparation

Trainee/ Junior Tradesmen

Prepare water, power tools, ensure batteries are fully charged

Set up mixing station

Prepare back blocking timber, and back blocking cement


Mid-level Tradesmen Check onsite material is same as purchase order and delivery docket.

Please take a photo of onsite material and send to Regina via 0433 799 357 or orders@drywallwa.com.au

Team Leader Prepare cutting list and mentioned if it is for ceiling finish, cornice finish or P50 finish

Double Storey Casual Labour (ensure at least four personnel on site) For loading purpose



#2 - Installing Plasterboard

Trainee/ Junior Tradesmen

Adhesive

Back blocking

Holding sheet

Mid-level Tradesmen + Team Leader Use collated screw gun to screw in, ensure screws are fix 200mm centre to tiles areas




#3 - After Installation

Team Leader

Double check manhole location before cutting it


Mid-level Tradesmen

Ensure drywall lining are square, straight and level.

Cut out the manhole and install the manhole frame



#4 - Cleaning up

Trainee/ Junior Tradesmen

Clean the site every day before leaving